2020
ROAD / LOCATION PROJECT NOTES
ALERT NEW LONDON RD - Schradin Rd to Ohio 126 Resurfacing (chip seal) Est cost: $90,540. Funding: BCEO
BECKETT RD fire station and Beckett Ridge Blvd Drainage improvements, resurfacing Est cost: $2,000,000. Funding: BCEO
BUTLER WARREN RD at LIBERTY WAY Intersection improvement - add EB left turn lanes and NB left turn lanes Est cost: $1,030,000. Funding: State OPWC, local
COX RD - Tylersville Rd to Liberty Way Resurfacing (asphalt) Est cost: $468,126. Funding: BCEO
CRESCENTVILLE RD - Windisch Rd to Centre Park Dr Resurfacing (asphalt) Est cost: $110,880. Funding: BCEO
GARVER ELLIOT RD - Bunker Hill Woods Rd to Woods Station Rd Resurfacing (chip seal) Est cost: $23,200. Funding: BCEO
KYLES STATION RD Culvert #03.532 Replacement Road closure necessary. Start: mid- Sept. Completion: 1 wk. Est cost: $20,000. Funding: BCEO FA
KYLES STATION RD Culvert #04.032 Replacement Road closure necessary. Start: early Sept. Completion: 1 wk. Est cost: $20,000. Funding: BCEO FA
KYLES STATION RD Culvert #05.139 Replacement Road closure necessary. Start: late Aug. Completion: 1 wk. Est cost: $12,000. Funding: BCEO FA
HAMILTON MASON RD Bridge #07.491 (over Gregory Creek) Replacement Est. cost: $1,800,000. Funding: State OPWC, local
Photo: Existing bridge - top view
Photo: Existing bridge - side view
HAMILTON NEW LONDON RD - Morgan Ross Rd to Layhigh Rd Resurfacing (chip seal) Est cost: $130,332. Funding: BCEO
LAYHIGH RD Culvert #02.185 Replacement Road closure necessary. Start: late Sept. Completion: 3 weks Est cost: $30,000. Funding: BCEO FA
LESAINT DR Bridge #00.072 (inside Ffd city limits) Repair - pour concrete bottom Road closure possible. Start: mid-Aug. Completion: 1 wk. Est cost: $30,000. Funding: BCEO FA
LeSOURDSVILLE WEST CHESTER RD at BECKETT RIDGE BLVD Intersection improvement -install roundabout Road closure necessary. Est. cost: $1,008,373 Funding: Fed, BCEO
MIDDLETOWN GERMANTOWN RD Bridge #00.393 Replacement Road closure necessary. Est cost: $200,000. Funding: BCEO
Photo: Existing bridge - top view
Photo: Existing bridge - side view
MUHLHAUSER RD Bridge #00.430 Repair - pour concrete bottom Road closure possible. Start: early Aug. Completion: 1 wk. Est cost: $30,000. Funding: BCEO FA
OHIO 73 at JACKSONBURG RD Intersection improvement - install roundabout

Partial intersection closure necessary. Start: summer. Completion: mid-2021. ODOT PROJECT.

Notice of July 20, 2016 public mtg

SCHRADIN RD - California Rd to Alert New London Rd Resurfacing (chip seal) Est cost: $57,104. Funding: BCEO
STATE LINE CENTER RD - Indiana & Eastern RR to Oxf Twp line Resurfacing (chip seal) Est cost: $150,970. Funding: BCEO
TRENTON RD - U.S. 127 to Riverside Dr (north) Resurfacing (chip seal) Est cost: $153,104. Funding: BCEO
TYLERSVILLE RD at Chantilly Dr Add turn lane Road closure necessary. Est cost: $354,000. Funding: Fed, BCEO
TYLERSVILLE RD - I-75 to Cox Rd, plus bridge over I-75 Roadway improvement - widening, phase 2. Construct additional WB lane. Re-stripe bridge over I-75 to include additional EB lane. Construction mainly at night. Est cost: $1,845,000. Funding: But Co
WOODS STATION RD - Garver Elliot Rd to Stillwell Beckett Rd Resurfacing (chip seal) Est cost: $7,372. Funding: BCEO
Various County roads Guardrail installation Funding: Fed
 
2021
ROAD / LOCATION PROJECT NOTES
BUTLER WARREN RD at BARRET RD Intersection improvement - install roundabout Road closure necessary. Est cost: $1,930,000. Funding: Fed, BCEO, City of Mason
BUTLER WARREN RD at WEST CHESTER RD and SOCIALVILLE FOSTER RD (War Co) Intersection improvement - realignment, install roundabout Project in conjunction w/ Warren Co. Est cost: $1,519,000
Public Information Documents
FIVE POINTS INTERSECTION (Ham Mason Rd, Tylersville Rd, Tuley Rd, Grand Blvd, Hancock Av) Intersection improvement - install roundabout Partial road closures necessary. Est cost: $2,458,000. Funding: Fed, BCEO, City of Hamilton
Public meeting displays / handouts (9/19/18)

News release: Notice of public mtg (issued 9/4/18)
MILLIKIN RD at LeSOURDSVILLE WEST CHESTER RD (south leg) Intersection improvement - install roundabout Est. cost: $900,000. Road closure necessary
OHIO 129 / LIBERTY WAY at I-75 Interchange modification Est cost: $23,327,000 Funding: Fed
Public information materials and exhibits
SCOTT RD Bridge #00.618 (over Darrs Run) Replacement Road closure necessary. Est cost: $2,082,000. Funding: Fed LBR
Photo: Existing bridge - top view
Photo: Existing bridge - side view
WAYNE MADISON RD at TRENTON RD Intersection improvement - install roundabout Partial road closures necessary. Est cost: $1,710,000. Funding: Federal, BCEO, City of Trenton
Public meeting displays / handouts (12/5/18)

News release: Notice of public meeting (issued 11/19/18)
 
2022
ROAD / LOCATION PROJECT NOTES
CRESCENTVILLE RD - Ohio 747 to I-75 overpass Roadway improvement - widen to 3 lanes (addition of center turn lane), drainage improvements Funding: Fed, City of Springdale, City of Sharonville, BCEO
 
2023
ROAD / LOCATION PROJECT NOTES
TYLERSVILLE RD - Lakota Springs Dr to Lakota Hills Dr Roadway improvement - add dedicated left turn lanes and center turn lane Road closure necessary. Est cost: $1,736,000. Funding: Fed, BCEO